Why can't i change project en date to "Project does not have an end date"?
-
Good question. I had the same issue. One reason is the scheduling method is set to JIT. But that didnt always work as a way to bring back the floating end date.
And why can't we use JIT with a system-calculated end. After all we want the scheduling system to calculate the duration. If I guess an end date to trigger JIT task scheduling it seems to impact other things.