Summary: Set a screen up once, save it as a custom view, and load it again in one step.
Applies to
| Property | Value |
|---|---|
| Product | LYNX-X |
| Version | 28.10.9888.0 |
| Required permissions | Anyone with a LYNX-X account |
| Last updated | 2026-11-17 |
| Owner | Support |
Before you start
- You are signed in to LYNX-X.
- A custom view is a saved set-up of a screen: its filters and the settings of the sub views it includes. You load it again in one step.
- A custom view is not one of the schedule views of a project, such as Schedule view or Critical chain view. See Which schedule view to use.
- Every custom view belongs to one scope, the group of screens it was saved on:
| Scope | Sub views it can include |
|---|---|
| My activities | Task list, Card list, Kanban |
| Portfolio | Project list, Resource load |
| Project | Gantt, Task list, Card list, Kanban |
| Active tasks | Task list, Card list |
Each scope keeps its own custom views and its own filters. A custom view saved on My activities sets up My activities, and one saved in a project sets up a project.
What a custom view brings back when you load it:
| Screen | Brought back |
|---|---|
| My activities | Role, Horizon, and filters set on columns, such as Task type |
| A project | The text in Filter tasks, filters set on columns of the grid next to the Gantt bars and of the Task list, and how the Gantt is divided between grid and bars |
| Project list | Filters set on columns, also on a custom field column. Debuffered, when it was on |
| Resource load | The period, the settings under Options, and toolbar buttons such as Stacked graph |
The sort order of a list is not kept. A column you added yourself is not put back either: see Example: projects of one business unit.
Procedure
The work has three steps: set the screen up, save it, and load it whenever you need it. The first example uses My activities and keeps the tasks you manage for the next four weeks.
Set the screen up
-
Open the screen. In the example: Focus > My activities. It opens with Role: All and Horizon: All.
-
Set the first filter. In the example: open Role and select Task manager.
- Set the next filter. In the example: open Horizon and select 4 weeks.
- If you want, filter a column too: right-click its header, for example Task type, tick the values to keep and select Apply.
- Check that the list shows what you want to come back to. Everything you set here goes into the custom view.
Save it as a custom view
- At the bottom of the left rail, select Custom views. The dialog opens on the scope of the screen you came from.
- Under New custom view, enter a Name. A Comment is optional and shows under the name in the list.
- Under Included views, leave ticked the sub views the custom view covers.
-
Select + Save as new view.
The custom view now shows under Saved views, with its scope and the sub views it includes.
Load it
- Open a screen of the same scope. It does not matter which filters are set at that moment.
- Select Custom views.
- Under Saved views, select Load on the row of the custom view.
The dialog closes and the screen shows the saved set-up.
Example: projects of one business unit
This example filters the Project list on a custom field, Business Unit.
The Project list before:
- Go to Portfolio > Project list.
- Right-click a column header, for example PM, and select Add column after….
- Type the first letters of the field, tick Business Unit [cf] and select OK. The column is added to the list.
- Right-click the header of the new column, tick the value you want, for example BU Energies, and select Apply. A funnel on the header shows that the column is filtered.
- Select Custom views, enter a Name, and select + Save as new view.
When you load this custom view later, add the Business Unit [cf] column first (steps 2 and 3). The custom view keeps the filter, and it filters the list when the column is on the list.
The Project list after loading the custom view:
A date column, such as End, has From and To fields in the same menu, for a filter on a period.
Filter further after loading
After loading, you can add more filters for the moment, for example a filter on a column. The saved custom view stays as it was. When you load it again, the screen goes back to the saved set-up and the filters you added are removed.
Example: the tasks of one skill, in every project
A custom view of the Project scope is not tied to the project you saved it in. Save it once, and load it in any project where you want the same view. The example keeps the tasks that need Mechanical Engineering and have not started yet.
A project's Gantt before:
- Open a project. It opens on its Gantt.
-
In Filter tasks, type the first letters of the skill, for example
mech. The Gantt keeps the tasks that have that skill next to their bar. -
Filter a column of the grid on the left of the bars. In the example: scroll the grid to the right with the scroll bar under it, to the Status column. Right-click the Status header, tick Not started and select Apply. A funnel on the header shows that the column is filtered.
- Select Custom views, enter a Name, for example Mech not started, and select + Save as new view.
- Open another project, select Custom views and Load. The Gantt of that project shows its own tasks for the same skill that have not started.
The Gantt of another project after loading the custom view:
The custom view also brings back how the Gantt was divided between the grid and the bars.
The Task list of a project has the same column menu: select Gantt at the top left, then Task list, and right-click a header. The text in Filter tasks also applies to the Task list, where it looks at the names shown in the list. Clear the box there when the list comes up empty.
Change or remove a custom view
To store new filters in a custom view, rename it, build a new one on top of it or delete it, see Changing a custom view.
Go back to the full list
To see the screen without your filters, without deleting the custom view:
- Right-click any column header of the list.
-
Select Clear all sorts and filters.
The list shows all its rows again. This also removes a filter on a column that is hidden. A column you added stays on the list, without its filter.
Filters outside the columns are cleared on their own:
- Clear the Filter tasks box with its ×. Clear all sorts and filters leaves the text in that box in place.
- On My activities, clear Role and Horizon with the × next to them.
Your custom view is not changed by this. Load it again to get back to the saved set-up.
Expected outcome
Your custom view is listed under Saved views in the Custom views dialog. One click on Load brings the screen back to the set-up you saved.
The top right of the dialog reads Loaded view: with the name of the custom view you loaded last. It adds (changes since loading) once you change the filters after loading.
After you sign in again, My activities opens in its standard state. Load the custom view to get your set-up back.
Troubleshooting
| Problem | What to do |
|---|---|
| Load is greyed out for a custom view | The custom view belongs to another scope. Open a screen of that scope, for example a project for a Project custom view, and load it there. |
| After Load, the list is not filtered on your custom field | The column of that field is not on the list. Add it with Add column after…, then load the custom view again. |
| The list comes back in a different order | The sort order is not part of a custom view. Sort the list again after loading. |
| The Task list of a project is empty after loading a custom view | The text in Filter tasks applies to the Task list too. Clear the box with its ×, or select Click here to clear all filters in the empty list. |
| Rows are still missing after you removed a column | A filter stays active when its column is hidden or removed with Restore columns. Right-click a column header and select Clear all sorts and filters. |
| Rows are still missing after Clear all sorts and filters | Look at the Filter tasks box and clear it with its ×. On My activities, also check Status, Role and Horizon. |
See also
- Changing a custom view
- Sharing custom views with your space