Summary: Set a screen up for a team, save it as a custom view with Share in space ticked, and the users of your space can load the same set-up.
Applies to
| Property | Value |
|---|---|
| Product | LYNX-X |
| Version | 28.10.9888.0 |
| Required permissions | Space owner |
| Last updated | 2026-11-17 |
| Owner | Support |
Before you start
- You know how to save and load a custom view. See Saving a screen set-up as a custom view.
- Decide which team the custom view is for and which screen they start from. Name it after the team, for example Resource manager view.
- Sharing is chosen at the moment the custom view is saved. Set the screen up first, then open the dialog.
Procedure
The example makes a Resource manager view: the portfolio in Debuffered, with Resource load on a period of six weeks.
Set the screen up for the team
-
Go to Portfolio > Project list. This is the screen the team starts from.
-
In the left rail, select Debuffered. A green banner Scenario: Debuffered shows that it is on.
-
In the left rail, select Res. load. Resource load opens in its own window.
- Select the period the team looks at. In the example: 6 weeks.
- Switch on the toolbar buttons the team needs, for example Stacked graph or Show allocations. They are saved with the custom view.
- If the team needs other settings, select Options in the toolbar and set them there, for example the scaling or the tick boxes. They are saved with the custom view as well.
A custom view keeps more than filters: what changes the look of the screen, such as these buttons, is saved with it. The two pictures show Resource load before and after loading a custom view that was saved with Stacked graph on.
Save and share it
- In the Resource load toolbar, select Custom views, next to Options.
- Under New custom view, enter the Name, and a Comment that tells the team what the custom view is for.
- Tick Share in space.
- Under Included views, leave ticked the sub views the custom view covers. In the example: Project list and Resource load.
-
Select + Save as new view.
Under Saved views, the row of the custom view reads Yes in the Shared column.
Check it from the standard screen
- Close Resource load and switch Debuffered off, so the Project list is back in its standard state.
- Select Custom views at the bottom of the left rail.
- Select Load on the row of the custom view. Debuffered switches on.
- Select Res. load. It opens on the saved period.
Loaded from inside Resource load, the custom view changes the period at once.
Expected outcome
The users of your space find the shared custom view under Saved views, marked Yes under Shared, and load it. Each of them gets the same set-up on the projects they can see.
From there, each user can filter further and save the result as a custom view of their own. For a user who is not a space owner, Overwrite with current settings, Save changes to selected view and Delete view are greyed out on the shared custom view, and so is Share in space. The shared custom view stays as you saved it. To change it later so that your colleagues get the new set-up, see Changing a custom view: overwriting it does not reach users who loaded it before.
Troubleshooting
| Problem | What to do |
|---|---|
| A custom view you saved earlier reads No under Shared | Sharing is not changed by Overwrite with current settings or Save changes to selected view. Load the custom view, tick Share in space, save it with + Save as new view, then delete the earlier one. |
| A colleague cannot tick Share in space | Sharing is for space owners. A colleague can save custom views for their own use. |
| Loading the custom view from the Project list does not show Resource load | The custom view sets the period, and Resource load opens when you select Res. load. |
See also
- Saving a screen set-up as a custom view
- Changing a custom view
Comments