Introduction
This article helps you to get started with LYNX for Critical Chain Project Management (CCPM). The following topics will be addressed:
- Downloading LYNX
- Registration and login
- Basic configuration
- Create your first project
- Executing the project
- Tips and tricks
You can also download the "Get started" PDF manual added at the bottom of this article. The PDF is a summary of this article and provides a visual overview.
This manual address the basic configuration to get going and helps you to add and release your first project.
Also refer to the article: LYNX Overview: Setting the Scene. Here you will find some background information on the underlying theories of LYNX.
Download LYNX
In order to use LYNX, you can download LYNX via https://www.a-dato.com/download-lynx/.
LYNX is supported on Windows and can be run on a Mac by installing a cross platform tool, like Parallels.
Registration and Login
Create your Account
To start using LYNX you have to register as a user. You can either register as a new user or login by invitation.
Register as new account and first user
After you have downloaded LYNX for the first time LYNX will ask you to register.
As a result of the initial registration process a "Default" workspace is automatically created, and as the first user you will become the "Spaceowner" for your "Default" space.
![]() |
You will receive an invitation to activate your account on this address, see figure:
![]() |
After selecting Activate Account , you will be asked to update your profile and set your password.
![]() |
After registration you can login with your email and password:
![]() |
Your first screen and workspace
Once you have registered, LYNX has automatically created a "Workspace" for you in the role of "Space owner".
In your workspace you can add your projects and the typical skills and resources (the resource / skill matrix) that would be assigned to projects and tasks. If you open Lynx, you will get the following view:
Explanation:
- Your first screen after starting LYNX is always the "My activities" screen.
- At the top of the screen the active Workspace is displayed. If you are a new user, the first part of you email address will be automatically the name of your space. The order of the displayed names is: First name & Last name, Company - Space name.
- If you are invited as a user the name of an existing workspace is displayed. In this example, Welcome to Lynx.
First user always receives the "Space owner" role
As the first user for a workspace you will automatically receive the Space owner role for your created workspace.
You can review this via the Users/Logins table as shown in the following picture:
![]() |
Invited to Lynx?
Most of the users in LYNX would become a new user through the sharing and invitation process and workflow. In this case you don't need to create an account: this is already done for you when you were invited by another user (e.g. Space owner).
In this case there is already a "Company" workspace and also a "Space owner" (typically the portfolio manager or system admin) who is sending out the first invitations to colleagues and team members inviting them to join the "Company" workspace, and in a specific role (e.g. Task manager, Team manager).
Invitation by Email from A-dato support
When you are invited to become a user in an existing workspace, you will receive the following Email:
![]() |
After selecting Activate Account, you can follow the same steps as when you Create your Account.
Your first screen after invitation
After you have logged in the following screen will be displayed:
Explanation:
- Your first screen after starting LYNX is always the "My activities" screen.
- At the top of the screen the active Workspace is displayed.
- If you are invited as a user the name of an existing workspace is displayed.
Login as LYNX TameFlow user
For those who would also like to access LYNX TameFlow, TameFlow can always be started via LYNX. However, team users, who only need to work with LYNX TameFlow can also just start using the separate LYNX TameFlow download link.
Please refer to Get Started with LYNX TameFlow for more detailed information on LYNX TameFlow.
You can use the same login credentials for logging in into LYNX TameFlow:
Do you want to change your profile or password?
Select Profile → My Profile to change your profile and also your password, as displayed in the picture below:
Forgot your password?
If you need a new password, you can easily request this via the login screen and by pressing the "Forgot" button:
This button is also available in Lynx Tameflow, see this figure.
Visit the LYNX Help Center
You are currently reading an article within our Help Center. The A-dato Help Center can also be found within Lynx when you need help at any point in time. Go to Help → Help center → Get started.
![]() |
How to create additional workspaces?
If you are new to LYNX you will automatically get your own demo space: "firstname.lastname space". This demo space can help you to explore some of the LYNX features. See this article for further explanation: Your personal demo space in LYNX.
Besides this demo space, there are two options to create a (new) space (see attached video):
- Create a new space:
- A new empty space is created, without any data. All configuration tables (calendars, skills, etc.) are empty
- The user that created the new space will be by definition the Space Owner and the only member or user of the new space
- Clone a current space:
- all data and tables are copied from the current space (projects, configuration, settings), except:
- the user-table is not copied and the person who "cloned" the space will be by definition the Space owner and the only user that has access to the cloned space
- all data and tables are copied from the current space (projects, configuration, settings), except:
Change the name of a workspace
-- If you are invited to a space, you (probably) don't want to change the name, because this changes the name for every user within this space.--
Add the desired workspace name or change the name of your workspace by editing the Space Properties, see figure below (Configure -> Space Properties):
Planning
Add your First Project
To get started on your first project select project portfolio in the desktop window (F5) → select add. Explanation: Several project properties are set in this step
- Each project receives a unique project ID and project name
- To start a new project a desired end-date has to be filled in
- There are different scheduling options you can select. For a CCPM project 'just in time' is considered the best practice.
Project Portfolio Window
You will now find your first project listed in the project portfolio tab. It is listed with status “not started”. Here you can filter projects on show all/ not started/ released. You can find this project under show all or not started initially.
Useful features you can use in the project portfolio window are illustrated below:
Project Window
After double clicking on the listed project in the portfolio window you will now be in the project window. A new tab will open at the top bar with the name of your project.
Select features include:
Create the Project Plan
In this step the following steps are covered in order to create a complete project plan:
- Add Tasks (and initial Prj. duration)
- Add Task Dependencies
- Add Skills and Resources
- Add Task Managers
- Convert the plan into a Critical Chain Plan
Target Plan
The below image shows the target plan that should be achieved after following the next steps in Add Tasks and Add Dependencies.
Add Tasks
You can add tasks via the add task button in the task grid.
Explanation:
- Upon giving the task a name the default task duration is set to 1 day. You can change the duration the the duration column.
- To confirm updates in the task duration you can click enter of click in the Gantt Chart to confirm the update.
- * Background of this process is the optimization of the performance and prevents that any (small) change triggers a re-calculation of the complete (large) project plan.
Add and edit more tasks
You can also add tasks via the plus button.
Note: This image illustrates the 'just in time' scheduling features, whereby tasks are not (yet) part of the "Critical Chain". The Critical Chain implementation will be illustrated in later steps.
Save your progress
Once adding all the tasks be sure to click Save. By clicking Save each task gets its own ID. By clicking on the Auto Scale time bar all the tasks will be automatically scaled to fit your window.
Note: update also the initial Prj.duration, you can also decide to this later
Add Task Dependencies
Task dependencies determine the relationships between tasks and identify which tasks need to be completed in order for other tasks to be performed. There are different ways to add dependencies between tasks in LYNX.
Add dependencies via the task grid
Add dependencies via the Gantt Chart
Note: The dependency is added in the direction of first select tasks to second
Add dependencies via the Edit Boxes
This method is especially useful for projects with many tasks
Delete Task Dependencies
In order to delete dependencies, select the task → go to task properties at the bottom of the screen → select the dependencies tab → delete the desired dependency in either the predecessor or successor box.
Add/Update Task Dependencies
Select view → select data entry view (Alt+F6) → you now have a visual of the number of predecessors and successors per task.
Review Results and Statistics
This should look similar to the Target Plan presented earlier.
Explanation:
- Task properties are displayed at the bottom when selecting individual tasks. Select the different tabs to edit task properties such as dependencies, resources etc. In the example the task properties of task #6 are detailed.
- On the right side of the screen you can view and review the project statistics.
Select Critical Chain View
Changing the view will only display tasks that are part of the critical chain.
Add Skills and Resources
The next step is adding the required skills and resources in order for the tasks to be performed. Once again there are several ways in which you can add them.
Add skills via drag & drop
Select the skills/resources window on the right side of your screen and drag and drop the desired skills to the selected tasks.
Add skills via the resource requirements column
Review the Resource Load
Once you have assigned diverse skills and resources you can review the total resource load of the project. This allows you to compare the resource availability versus resource scheduling. In the below example the red shaded area illustrates that there is not enough resource availability.
Modify Task Estimated Time and Units
One way to resolve overload in resource availability is to modify the time required for each skill/resource. You can also easily edit resource requirements in this way.
Note: once skills or resources are assigned to a task, you can not update the task duration via the column Prj.duration anymore, and the duration is shown in [6] brackets. The possibility to update durations has "moved" to the resource requirements box, as indicated below
Scenario Virtual Skills: Review Resource Load
In the case of scheduling “Virtual Skills” LYNX does not make a pre-selection and soft-allocates a resource name. Please refer to the manual on resource and skill assignment for an in-depth explanation.
Add Task Managers
The next step is adding who is responsible for which task, also referred to as task managers. In a CCPM implementation typically a Task Manager is responsible for (daily) task updates.
Add Task Managers through invitation
Explanation:
-
Invite Multiple Task Managers involved to the TM list. Task Managers are typically responsible for providing tasks updates, often on a daily basis.
-
Inviting a Task Manager via the Task Property tab at the bottom will only invite a TM for that specific task.
-
Inviting a TM through the Task Manager list will invite them for the project, after which you can assign them individually per task.
Add Tasks Managers via the Task Manager column or via Drag & Drop
Apply Critical Chain Behavior
There are three steps involved in applying Critical Chain Behavior to the project:
Explanation:
- The first step implements the Critical Chain Project parameters. In this example tasks are automatically shortened by 50%.
- The second step allows us to determine the type of buffers you wish to insert.
- Finally, the buffers are implemented. Buffers have been added to the project and the length of the critical chain has been shortened by 50%.
Video Explainer: How to Create your First Project
See this video demonstrating how to create your first project. (This is a HD Video you can watch fullscreen on Youtube. Select settings in Youtube and set quality to 720P or 1080P)
Start a Project from a Template
You can find new templates under the project portfolio → templates
Next, select Add to create a new project from an existing template.
You can now find your new project under not started.
Releasing your Project
Releasing the Project and its Tasks
Once you have completed the project planning it is time to release the project. This can be done by selecting Properties → Select status: Released.
Explanation:
- The release of the project has extended the statistics window. You can now find additional statistics key to controlling your project.
- After the release, LYNX has now created two buffer controls. The project buffer column and feeding buffer column can now be found next to each task.
My Activities Window
You can now select the My Activities window in the desktop window. This screen adds several features and allows Task Managers to:
- Assign and confirm resources for a task
- Start a task by changing the status
- Enter the Estimated Time to Complete (Ettc).
The below visual illustrates how:
Tips and Tricks
Search and Replace (CTRL+F)
To quickly find projects or items you are looking for use CTRL+F to open the advanced search tool:
Mark Favorites
To highlight favorites or often used roles select the skills tab and select roles often used. These roles will now appear on top of the list when opening the skills tab:
Basic Tips & Tricks
Explanation:
- Filter or hide columns by right clicking on the column header.
- You can copy a selection of tasks in the task column by using CTRL C and CTRL V.
- You can zoom into the Gantt chart by clicking on it and using your scroll button.
- Zoom in and out in the Gantt chart by moving the date lines (drag with mouse).
- The viewing tab gives you an overview of different viewing options to gain different insights.
Explanation:
- Right click on a project row to get quick access to the progress chart or to copy a project.
- Right click on the column header to add/remove any filter.
- Windows can be individually moved, making it easy to use two screens side by side.
Resolve Warning Messages
There are several reasons you could receive a warning message such as: plan cannot be calculated due to planning logic violations. See the following example:
Explanation:
- This example illustrates two warning messages. These are listed under the task properties messages tab. Also the project statistics box includes message "there is a problem with this project, see messages tab."
- In this example two designers have been scheduled, but only one is available. The maximum availability has been exceeded.
- The second error is related to task dependencies. A dependency may have been accidentally added in the wrong order and can be deleted to resolve the error.
Add Notes
In the project you can add notes to different tasks as required. Select the notes icon → the notes pop up will open (task details) → click on the plus icon to create a new note → select the type of note you want to add:
Additional Resources
Please also refer to the following articles for more in-depth information and quick insights into the following topics:
- LYNX Overview: Setting the Scene
- Skill and Resource Configuration
- Calendar, Time and Durations
- User Roles and Adding Users by Invitation
Download the manual!
Comments
0 comments
Article is closed for comments.