Summary: Every LYNX-X article on resources and capacity, grouped by what you want to do.
In LYNX-X, this topic covers what you need to set up skills, people and calendars, assign people to work and check the load across projects. Go straight to the part you need: every article says what it is for and how long it takes to read.
In this topic
| Part | What it covers | Articles |
|---|---|---|
| Set up skills and resources | The skill, resource and team model, and how to create skills and resources | 2 |
| Calendars and availability | Working time, part-time people, absences, and which calendar a task follows | 5 |
| Assign people to work | Choose between a skill and a named person, and firm up assignments when the work gets close | 2 |
| Check workload across projects | See where demand exceeds capacity and what one person is committed to | 1 |
Set up skills and resources
The skill, resource and team model, and how to create skills and resources.
Understand
- Understanding the skill, resource and team model: resources and skills have a many-to-many relationship in LYNX, and properties let you narrow a skill down to the specific competency a task needs. About 3 minutes of reading.
Do
- Configuring skills and resources: find the skills and resources already in the space, and add, edit or remove a skill from a resource. About 2 minutes of reading.
Calendars and availability
Working time, part-time people, absences, and which calendar a task follows.
Understand
- Which calendar a task follows: a task's working time comes from the calendar of whoever does the work (the resource behind a skill, or a Virtual skill's own calendar), while the project's calendar and Hours per day decide how that time is counted in days. About 5 minutes of reading.
- What 100 % means: choosing how to model availability: three settings can each stand for "100 %" (the working day, a resource's netto availability and an assignment's units). This article follows one person who gives 75 % of his time to projects through four ways of modelling it, so you can choose the one that fits how your team plans. About 7 minutes of reading.
- Working with unit percentages: units is the share of an assignment's hours that a resource actually contributes. It is the number that turns a span of days into an amount of work. About 3 minutes of reading.
Do
- Setting up a calendar: create a calendar that defines an organisation's working hours and non-working days, so that projects, resources and skills can be scheduled against it. About 3 minutes of reading.
- Setting a resource's non-availability period: add a specific exception to a resource's availability (a holiday or other absence) separately from their assigned calendar. About 2 minutes of reading.
Assign people to work
Choose between a skill and a named person, and firm up assignments when the work gets close.
Do
- Converting a soft assignment to a hard assignment: confirm LYNX-X's recommended resource into a named one, by choosing the resource yourself, or by letting the start of the task do it for you. About 4 minutes of reading.
- Pre-selecting a resource pool for a project: narrow a project down to a maximum number of resources, or a named selection, before assignments are made (a "dream team" pre-selection). About 3 minutes of reading.
Check workload across projects
See where demand exceeds capacity and what one person is committed to.
Look up
- Reading multi-project resource load: the resource load view in Project Portfolio shows average load per skill across projects, and can unfold to the underlying resources and their non-availability periods. About 3 minutes of reading.
Learn it step by step
These learning paths use the articles in this topic, in an order for your first session:
- Learning path: Manage skills, people and capacity: Set up skills and people so that LYNX-X plans with the capacity you really have, and see where projects ask more of a skill than your people can give.