Summary: Below the task grid of a project, the selected task's details sit on a row of tabs. This page says what each tab holds and where to go to change it.
Applies to
| Property | Value |
|---|---|
| Product | LYNX-X |
| Version | 28.10.9877.0 |
| Required permissions | Any user who can open the project |
| Last updated | 2026-11-09 |
| Owner | Support |
Overview
Open a project and select a task in the grid. Below the grid, a bar shows the task's ID, its status, its name and three boxes, CC, CLC and RTS. Under the bar is a row of tabs. Until you select a tab, the panel shows only these names, also right after you add a task. Select General to see the task's main fields.
Select the status to change it: Not started, Started, Completed, Paused or Aborted. Not every task has every tab. A workpackage has an extra Workpackage tab, and a buffer row has no status and no Assignments or Taskmanagers tab. The number after a tab name, such as Assignments (3), counts what is on it.
Nothing you change on a tab is stored until you select Save at the top of the left rail.
Fields
General
| Field | What it is |
|---|---|
| Duration | How long the task takes. A duration in brackets, such as [16 days], comes from the task's assignments. |
| Ettc | Estimated time to complete: the working time still needed, counted from tomorrow. See Updating a started task. |
| Task type | Normal, Milestone, Workpackage, Level of effort, Summary task, or one of the buffers. A workpackage holds cards. A level of effort task holds continuing coordination or management effort, often across a phase, that you do not want on the critical chain. See Choosing a task type (normal, milestone, level of effort, workpackage). |
| Priority | The task's own priority. See Why one task comes before another. |
| Auto complete | Lets the remaining time count down by itself. See Using auto-complete tasks. |
| Fixed duration | For work that takes a set time whatever CCPM does with the plan, such as procurement or sourcing material. |
| Show task in Tameflow? | Turns the task into a card you work on a TameFlow board. Without it, the task appears on a task board only. The task needs someone in a role on it, such as a task manager. |
| Critical chain task?, On current longest chain?, Ready to start? | Set by LYNX-X, not by you. They are the CC, CLC and RTS boxes on the bar. Ready to start means every task before it is complete. |
| Comment | A short remark about the task. |
Staging
| Field | What it is |
|---|---|
| Stage | The stage of the project this task belongs to. The list offers the stages of the project's stage plan; it is empty while the project has no stages. |
| Stage start, Stage stop, Stage duration | The dates and length of that stage. |
The Staging tab is there only when staging is switched on in Space properties.
Dates
| Field | What it is |
|---|---|
| Baseline | The task's start and stop when the project was first released. |
| Scheduled | The start and stop LYNX-X plans now. You cannot type here. |
| Actual | When the task really started and stopped. LYNX-X fills the start when the task is set to Started and saved, and the stop when it is set to Completed and saved. You can change either if it is not right. |
| Stop on start | Shown once the task has started: the finish date planned at the moment it started. Finishing after this date may use buffer. |
| Constraint, Deadline | Rules for where the task may sit in the plan. See Setting task constraints and deadlines. |
| MS constraint | Shown on tasks that lead to a milestone: the deadline of that milestone. It tells you which milestone date the task works towards. You cannot type here. |
Custom fields
The fields your space adds to tasks. Which ones you see depends on your space. See Setting up custom fields.
Visual
| Field | What it is |
|---|---|
| Bar fill color, Bar edge color, Bar start image, Bar stop image | The look of the task's bar in the Gantt chart. |
| Default bar label, Custom bar label | The text shown above the bar. Tick Use task description as label, or type your own. |
Assignments and links
| Tab | What it is |
|---|---|
| Assignments | The skills and resources the task needs. See Adding a skill or a task manager to a task. |
| Taskmanagers | Who reports progress on the task. See Adding a skill or a task manager to a task. |
| Predecessors, Successors | The tasks before and after this one. See Adding task dependencies. |
On each of these tabs, Assign opens the Drag & drop to task panel on the right with the matching list.
Workpackage
Only on a workpackage. WP Size is the work reserved for the workpackage, Size from cards the work its cards hold, and Remaining size (open cards) the work on cards not yet done. When the cards hold more than the WP Size, a red message says so. See Adding a workpackage and cards via the Cards view.
Notes
- After you set a task to Started or Completed, select Save. Its actual date appears on the Dates tab once the project is saved.
- To see more of a tab, drag the line between the grid and the tabs upwards.