Summary: Put a project or a task on hold, or stop it for good, and know what that changes in the plan.
Applies to
| Property | Value |
|---|---|
| Product | LYNX-X |
| Version | 28.10.9885.0 |
| Required permissions | A project: its project manager, or the PMO or space owners. A task: a project manager or task manager. |
| Last updated | 2026-11-16 |
| Owner | Support |
What each status means
A project has one of five statuses:
| Status | Meaning |
|---|---|
| Not started | The project is being prepared. Its tasks are not active yet. |
| Released | The project is active. Its tasks reach My activities and Active tasks. |
| Paused | The project is on hold and is meant to resume. Its tasks are not active. |
| Completed | The project has finished. |
| Aborted | The project has stopped for good. |
A task has one of five statuses: Not started, Started, Completed, Paused (on hold, meant to resume) and Aborted (stopped, will not continue).
Paused or aborted?
The two look alike, but they do very different things to the plan:
| Paused | Aborted | |
|---|---|---|
| A task | stays in the plan as it is: on the current longest chain, with the same expected finish | leaves the plan: the chain counts it as done, and the tasks after it can start |
| A project | leaves the released projects: its tasks leave Active tasks and its work leaves the portfolio resource load | leaves the released projects, and is not meant to come back |
Before you start
- A project is paused or aborted by the people who release it: its project manager. When the space does not let project managers release projects (Project managers can release projects cleared in Space properties, on the Turn features on/off tab), the PMO or the space owners do it. See Releasing a project.
- A task is paused or aborted by its project manager or a task manager: anyone who can change the task's status.
- Decide whether you want to resume the work later (Paused) or stop it for good (Aborted).
Procedure
Pause or abort a task
- Open the project and select the task.
-
In the task panel, select the status beside the task's ID and choose Paused or Aborted.
-
Select the tick at the top left of the task panel to apply the change.
- In the left rail, select Save.
Pause or abort a project
- In the top bar, select Portfolio, then Project list.
- Select the project. A released project is under the Released filter.
- In the left rail, select Properties.
-
On the General tab, open the Status list and select Paused or Aborted.
-
Select OK.
Resume
- A task: select its status again and choose the status the work is in now. Apply with the tick and Save.
- A project: select Show all in the Project list to find it, open Properties, set Status to Released and select OK.
Both status lists offer all five statuses when the project or task is Paused or Aborted, so either can be set back.
Expected outcome
A paused task stays in the plan as it was. It stays on the current longest chain, its bar does not move, and the project's expected finish does not change. It also stays in Active tasks, where its status reads Paused.
An aborted task leaves the current longest chain and Active tasks. The chain counts it as done, so the project's expected finish can move earlier. The tasks that waited for it become Ready to start.
A paused or aborted project leaves the Released list of the Project list, and it is not under Not started either. Select Show all to find it: its status reads Paused or Aborted, and Expected finish and Performance show n/a.
The tasks of a paused project leave Active tasks, and its work leaves the portfolio resource load. Set it back to Released and its tasks and work return.
Additional information
- Pausing a task does not take it out of the plan: it keeps its place on the chain and in the schedule.
- Use Aborted for work that will not be done. The chain counts an aborted task as done, so the project's expected finish can move earlier and the tasks after it become ready to start.
- To record why you paused or aborted something, add a note to the project or task.
Troubleshooting
| Problem | Resolution |
|---|---|
| A project is missing from the Project list, and it is not under Not started. | It may be paused or aborted. Select Show all. |
| A project's row shows n/a for Expected finish and Performance. | The project is paused, aborted or completed. Read its Status. |
| A paused task still shows in Active tasks. | This is expected: a paused task stays, with the status Paused. |
| You aborted a task by mistake. | Set its status back to Not started, apply with the tick and Save. The plan returns to its earlier shape. |
See also
Revision history
| Version | Date | Author | Changes |
|---|---|---|---|
| 1.0 | 2026-11-16 | Support | New article. |