Summary: Attach a calendar to a resource, a virtual skill or a project so that scheduling respects that calendar's working hours and non-working days.
Applies to
| Property | Value |
|---|---|
| Product | LYNX-X |
| Version | 28.10.9877.0 |
| Required permissions | Space owner (resources and skills); read and write access to the project (project calendar) |
| Last updated | 2026-11-10 |
| Owner | Support |
Before you start
- The calendar must already exist. See Setting up a calendar.
- Know which resources, virtual skills or projects need a calendar other than the one they have.
Where the calendar belongs
| You plan with | The calendar that counts | Set it on |
|---|---|---|
| A Normal skill | The calendar of each resource who holds the skill | The resource |
| A Virtual skill | The skill's own calendar. A virtual skill has no people, so an individual absence cannot be set on it: to give the whole skill fewer working days, for example a four-day week, assign it a calendar with those days | The skill |
| The project as a whole | The project's calendar | The project |
To take one person out for a holiday or a day off, do not change their calendar: set the absence on the resource instead. See Setting a resource's non-availability period.
Procedure
Assign a calendar to a resource
- Open Configuration, then select Resources.
- Select the resource.
- On the Details tab, open the Calendar list and select the calendar. The list offers the calendars that exist in your space.
- Select Save in the left rail.
Assign a calendar to a virtual skill
- Open Configuration, then select Skills.
- Select the skill. Its Skill type is Virtual.
- Open the Scheduling tab.
- Under Skill calendar, open the Calendar list and select the calendar.
- Select Save in the left rail.
Assign a calendar to a project
- Open the project's Properties, General tab.
- Select the calendar in the Calendar field.
- Check Hours per day: it must agree with the working hours of the calendar you selected. See Which calendar a task follows.
- Select OK. If Save in the left rail then shows a count, select it.
Expected outcome
The Calendar field shows the calendar you selected. Which calendar a task then follows, when a project, a skill and a resource each have one, is explained in Which calendar a task follows.
See also
- Setting up a calendar
- Setting a resource's non-availability period
- Which calendar a task follows
- How resource availability affects task duration
Revision history
| Version | Date | Author | Changes |
|---|---|---|---|
| 1.0 | 2026-11-10 | Support | New article. |
Comments
0 comments